Project Management Consultant |
Nitin Bhalerao, Pune |
Contractor |
Harsh Construction Pvt. Ltd. |
Scope of work |
SR.TYPE NOS.OF Qtrs NO OF Bldg TOTAL QTrs AREA PER Bldg = TOTAL Sq. mt.
1 Type A (Stilt+7) 28 02 56 2513.584 = 5027.168
2 Type B (Stilt+7) 56 01 56 5010.287 = 5010.287
3 Multipurpose Hall(G+1) -- 1 -- 1670.35 = 1670.35
4 Reading Hall(G+1) -- 1 -- 216.63 = 216.63
TOTAL NOS. OF QUARTERS 112
TOTALBUILT UPAREA= 11924.435Sq. mt. |
Project Exp.Cost (Rs in lakh) |
3781.24 |
Tendered Cost (Rs in lakh) |
3470 |
Date of Completion of Project |
15/06/2020 |
Period of completion (in month) |
24 |